Which of the following top down methods is used when projects closely follow past projects?

As a project manager, it's your responsibility to create a project budget and a project timeline that are both realistic and attainable. There are different techniques that a project manager can apply when planning for their projects, such as bottom-up, analogous, and parametric. However, these techniques do not necessarily work on all kinds of projects. Another estimating technique that is worth learning is the top-down estimating technique.

What is top-down estimating in project management?

Top-down estimating happens when the project managers need to produce a cost estimate or timeline of a project without any detailed information. It is a form of analogous estimating, where existing knowledge of similar projects is used in the estimation process to produce a ballpark figure for the total cost.

In top-down estimating, the initial project budget or time estimates come from the opinions of experienced managers and sometimes outside experts. Management can also predict actual costs and duration using similar past projects. These numbers can be tweaked to account for particular characteristics or aspects of the current project.

The cost accuracy depends on how closely the new project mirrors the previous similar project that the estimate is based on, or the previous experience of senior managers involved in the project estimates. When using top-down estimating for project planning, you will expect detailed bottom-up estimates, based on the costs of each work package, to replace the initial top-down estimates as time passes.

Top-down vs bottom-up estimating

Aside from top-down estimating, another method frequently used by project managers is the bottom-up approach. You can use these methods interchangeably, depending on the complexity and size of the project. But, which is better: the top-down or bottom-up approach?

Bottom-up estimation in project cost management is when the project team identifies all the project components and determines the lowest level component to derive estimates. These estimates cover the project scope in its entirety by calculating the cost of each of the project tasks. It's easy to see why bottom-up estimating is often called detailed estimating.

Compared to top-down estimating, bottom-up approaches involve all project team members as early as the project planning stage. Then, the project team works together to determine the required and critical tasks to complete the project. By including the whole team in the planning, you can get a time estimate for each project task, which will add up to the entire timeline of the project. This is in comparison to the top-down approach, which starts from the overall time estimate and then breaks it down to the different project tasks.

So, which is the better cost estimate?

The two estimating techniques both hold advantages and disadvantages. If your project has a clear direction and your team understands how the project is in line with the company goals, then top-down estimating is a suitable choice. Repeatable projects also fit well with the top-down approach because it relies on reliable historical data, which you can derive from similar previous projects.

However, a bottom-up approach will be suitable if the project is brand new or your team does not have any experience yet in doing such projects. This is because there exists a brainstorming of ideas and details in bottom-up estimating. Your project team may think of unconventional ways to get the task done in a shorter time without sacrificing the end result.

To become as efficient as possible, it is essential to first leverage the two methods before you can decide which estimating technique to use.

When are top-down estimates used?

Top-down estimation is frequently used when the project is still at an early stage. This estimating technique uses the most likely estimate for the project when the level of details is still limited. Here are some instances where the top-down estimating technique works well.

Developing technologies

Technology is rapidly evolving. This pushes companies to either develop their own technology infrastructure or improve it. During these situations, a top-down approach will be helpful. Management will provide top-down estimates of the project costs and the project schedule to create an initial plan, which they can pass on to the company's IT department.

Once received, the IT department will evaluate and derive the specific project costs. They can also create a more detailed plan from the initial one provided by management. This will involve details of the project schedules and resources required.

The top-down cost estimating process is also used when technology companies develop goods and services that consumers can purchase. For example, companies selling mobile devices such as phones and tablets may use a top-down approach in developing their new model devices.

Construction of buildings

When a company is experiencing steady growth, it might decide to move their headquarters to a custom-designed building. Companies often use the top-down approach to create company buildings, whether for offices, satellite locations, or even branches.

When they use the top-down approach, managers decide whether the company needs a new building and where it will be situated. Then, with the help of outside experts, other managers, and data from previous projects, the manager can lay out a tentative plan and budget for the construction of the building. The plan will not contain the specifics of the construction project, such as the material and labor costs, procedure for the construction, and accounting for the project. Instead, as the project details become more specific, such information will be adjusted.

The top-down approach paints the big picture of the project, and details are added to it once project managers become sure of the costs and time. Nevertheless, generating estimates from this technique takes less time and effort than other methods.

What are the advantages of the top-down approach?

Like other techniques, top-down estimating has its benefits and setbacks to project managers and the team. Here are some of the advantages of using a top-down estimate for your next project.

Useful for initial decision-making by the project manager

We mentioned before that the project management body provides the initial estimated cost and duration in top-down decision-making. It forms a broad estimate of the time and cost of the final deliverable. Having this information quickly available makes pivotal decision-making easier during the early stages of the project, especially when the details are still minimal.

Estimates are flexible

The top-down approach uses ballpark estimates of time and costs for the project. These estimates are derived from various sources, such as the project accounts from similar projects completed in the past or opinions from outside experts. However, as the project progresses, the estimates are adjusted as more details become available. This makes the planning more realistic and attainable.

Takes less time and effort

Because the top-down estimating technique focuses more on estimating the overall costs and duration of the project rather than its components, this technique generally takes less time and effort. This is useful when making initial decisions in the project when all the project specifics are not yet defined.

Uses more holistic data

The top-down approach to estimating uses data from previous projects and/or products to generate a time and cost estimate. This means that all risks, whether unforeseen or not, are taken into consideration. Other than that, top-down estimating also considers any scope creep that might happen during the project's duration.

The use of historical data in estimation relatively reduces any risk of overlooked tasks or costs in the project, making the estimates larger than those derived from other methods.

Disadvantages of the top-down approach

However, the top-down approach is not always applicable to every project you will have. Here are some disadvantages of top-down estimating.

  • It depends heavily on reliable data sources: if the historical data you are using is out of date or out of context, your top-down estimate could be way off.
  • It is usually limited to senior managers and stakeholders in the organization. Resources may experience a loss of planning control in the project, compared to a bottom-up estimate which involves the entire company.

Conclusion

Estimating project details is a huge factor in project planning. Time and cost estimates will heavily affect the quality of work your teammates will produce and the quality of the project itself. This is why project estimating techniques exist to ensure that all aspects of the project are realistic and reasonable.

Having the right software for your team can make a huge difference to the time it takes to prepare a cost estimate. Whether you are looking for a detailed bottom-up approach, or a top-down ballpark figure, being able to view the costs and resource breakdown for each of your past and ongoing projects is a valuable asset.

Interested in how Runn resource management software can help you produce more accurate cost estimates? Book a demo today!

Since estimating efforts cost money, the time and detail devoted to estimating is an important decision. Yet, when bottom up or top down estimates are considered, you as a project manager may hear statements such as these:

  • Rough order of magnitude is good enough. Spending time on detailed estimating wastes money.
  • Time is everything; our survival depends on getting there first! Time and cost accuracy is not an issue.
  • The project is internal. We don’t need to worry about cost.
  • The project is so small, we don’t need to bother with estimates, Just do it.
  • We were burned once. I want a detailed estimates of every task by the people responsible.
  • However, there are sound reasons for using top down or bottom up estimates.

The table below depicts conditions that suggest when one approach is preferred over another.

Condition    Top Down
   Bottom Up
Strategic decision-making Yes  
Cost and time important   Yes
High uncertainty Yes  
Internal, small project Yes  
Fixed price contract   Yes
Customer wants details   Yes
Unstable scope Yes  

Top Down Estimates Overview

Top Down estimates usually are derived from someone who uses experience and/or information to determine the project duration and total cost. These estimates are sometimes made by top managers who have very little knowledge of the processes used to complete the project.

For example, a mayor of a major city making a speech noted that a new law building would be constructed at a cost of $23 million and would be ready for occupancy in two and one-half years. Although the mayor probably asked for an estimate from someone, the estimate could have come from a luncheon meeting with a local contractor who wrote an estimate (guesstimate) on a napkin.

This is an extreme example, but in a relative sense this scenario is frequently played out in practice.

  • Do these estimates represent low-cost, efficient methods?
  • Do the top down estimates of project time and cost become a self-fulfilling prophecy in terms of setting time and cost parameters?

If possible and practical, you want to push the estimating process down to the work package level for bottom-up estimates that establish low-cost, efficient methods. This process can take place after the project has been defined in detail. Good sense suggests project estimates should come from the people most knowledgeable about the estimate needed. The use of several people with relevant experience with the task can improve the time and cost estimate.

Top Down Estimates, most used methods.

At the strategic level top down estimates are used to evaluate the project proposal. Sometimes much of the information needed to derive accurate time and cost estimates is not available in the initial phase of the project—for example, design is not finalized. In these situations top down estimates are used until the tasks in the WBS are clearly defined.

Consensus Methods

This method simply uses the pooled experience of senior and/or middle managers to estimate the total project duration and cost. This typically involves a meeting where experts discuss, argue, and ultimately reach a decision as to their best guess estimate. Firms seeking greater rigor will use the Delphi Method to make these macro estimates.

It is important to recognize that these first top down estimates are only a rough cut and typically occur in the “conceptual” stage of the project. The top down estimates are helpful in initial development of a complete plan. However such estimates are sometimes significantly off the mark because little detailed information is gathered. At this level individual work items are not identified. Or in a few cases, the top down estimates are not realistic because top management “wants the project.”

Nevertheless, the initial top down estimates are helpful in determining whether the project warrants more formal planning, which would include more detailed estimates. Be careful that macro estimates made by senior managers are not dictated to lower level managers who might feel compelled to accept the estimates even if they believe resources are inadequate.

Although I prefer to avoid the top down approach if possible, I have witnessed surprising accuracy in estimating project duration and cost in isolated cases.

Some examples are building a manufacturing plant, building a distribution warehouse, developing air control for skyscraper buildings, and road construction.

However, I have also witnessed some horrendous miscalculations, usually in areas where the technology is new and unproven.

Top Down estimates can be useful if experience and judgement have been accurate in the past.

Ratio Methods

Top Down estimates (sometimes called parametric) usually use ratios, or surrogates, to estimate project times or costs. Top Down estimates are often used in the concept or “need” phase of a project to get an initial duration and cost estimate for the project.

For example, contractors frequently use number of square feet to estimate the cost and time to build a house; that is, a house of 2,700 square feet might cost $160 per square foot (2,700 feet X $160 per foot equals $432,000). Likewise, knowing the square feet and dollars per square foot, experience suggests it should take approximately 10 days to complete.

Two other common examples of top down estimates are the cost for a new plant estimated by capacity size, or a software product estimated by features and complexity.

Apportion Methods

This method is an extension to the ratio method, apportionment is used when projects closely follow past projects in features and costs. Given good historical data, estimates can be made quickly with little effort and reasonable accuracy.

This method is very common in projects that are relatively standard but have some small variation or customization. Anyone who has borrowed money from a bank to build a house has been exposed to this process. Given an estimated total cost for the house, banks and the Housing Authority authorize pay to the contractor by completion of specific segments of the house.

For example, foundation might represent 3 percent of the total loan, framing 25 percent, electric, plumbing and heating 15 percent, etc. Payments are made as these items are completed.

An analogous process is used by some companies that apportion costs to deliverables in the WBS (Work Breakdown Structure)—given average cost percentages from past projects. The figure below presents an example similar to one found in practice.

Allocating project costs using a WBS

Assuming the total project cost is estimated, using a top down estimate, to be $500,000, the costs are apportioned as a percentage of the total cost. For example, the costs apportioned to the “Document” deliverable are 5 percent of the total, or The sub-deliverables “Doc 1 and Doc-2” are allocated 2 and 3 percent of the total—S10,000 and $15,000, respectively.

Function Point Methods for Software and System Projects

In the software industry, software development projects are frequently estimated using weighted macro variables called “function points” or major parameters such as number of inputs, number of outputs, number of inquiries, number of data files, and number of interfaces. These weighted variables are adjusted for a complexity factor and added. The total adjusted count provides the basis for estimating the labor effort and cost for a project (usually using a regression formula derived from data of past projects). This latter method assumes adequate historical data by type of software project for the industry—for example, MIS Systems uses them.

In the U.S. software industry, one-person month represents on average five function points. A person working one month can generate on average (across all types of software projects) about five function points. Of course each organization needs to develop its own average for its specific type of work. Such historical data provide a basis for estimating the project duration. Variations of this top down approach are used by companies such as IBM, Bank of America, Sears Roebuck, HP, AT&T, Ford Motors, GE, DuPont and many others.

See the tables below for a simplified example of function point count methodology.

Simplified basic function point count process for a prospective project Example: Function point count method

From historical data the organization developed the weighting scheme for complexity found in Table 1. Function points are derived from multiplying the number of kinds of elements by weighted complexity. Table 2 shows the data collected for a specific task or deliverable: Patient Admitting and Billing—the number of inputs, outputs, inquiries, files, and interfaces along with the expected complexity rating. Finally, the application of the element count is applied and the function point count total is 660.

Given this count and the fact that one-person month has historically been equal to 5 function points, the job will require 132 person months (660/5 = 132). Assuming you have 10 programmers who can work on this task, the duration would be approximately 13 months. The cost is easily derived by multiplying the labor rate per month times 132 person months. For example if the monthly programmer rate is $4,000 then the estimated cost would be $528,000 (132 X 4,000).

Although function point their accuracy depends on adequate historical data, currency of data, and relevancy of the project/deliverable to past averages.

Learning Curves

Some projects require that the same task, group of tasks, or product be repealed several times. Managers know intuitively that the time to perform a task improves with repetition. This phenomenon is especially true of tasks that are labor intensive. In these circumstances the pattern of improvement phenomenon can be used to predict the reduction in time to perform the task. From empirical evidence across all industries, the pattern of this improvement has been quantified in the learning curve (also known as improvement curve, experience curve, and industrial progress curve), which is described by the following relationship:

Each time the output quantity doubles, the unit labor hours are reduced at a constant rate.

In practice the improvement ratio may vary from 60 percent, representing very large improvement, to 100 percent, representing no improvement at all. Generally, as the difficulty of the work decreases the expected improvement also decreases and the improvement ratio that is used becomes greater. One significant factor to consider is the proportion of labor in the task in relation to machine-paced work. Obviously, a lower percentage of improvement can occur only in operations with high labor content.

The main disadvantage of top down estimates is simply that the time and cost for a specific task are not considered. Grouping many tasks into a common basket encourages errors of omission and the use of imposed times and costs.

Micro estimating methods are usually more accurate than macro methods.

Última postagem

Tag